|
Meeting 1
|
Transition Board
Transmission Work Group
|
April 1, 1997
|
The work group had its first meeting at the Northwest Power Planning Council’s
offices, with about 40 attending. Transition Board member Todd Maddock welcomed
the group and announced that Al Wright had been asked to chair the work group.
The first order of business was a quick review of the work plan. The group
then moved on to discussion of what was intended to be achieved. It arrived at a
list of six goals, most of which are drawn from the recommendations of the
Comprehensive Review. The group recognized that it may not be possible to fully
realize all the goals simultaneously (quotes are from the report of the
Comprehensive Review Steering Committee):
Goals
- "The primary goal of the Steering Committee’s recommendations for
transmission is a transmission system whose structure and operation help
ensure a fully competitive generation market. . . . Bonneville’s
generation and transmission systems should be separated to promote
competitive practices and to avoid the problem of self-dealing between the
generation apparatus and the transmission system."
- ". . . the formation of an independent grid operator, regulated by
FERC and including the transmission assets of the Bonneville Power
Administration and other owners of major transmission assets in the
region."
- "Legislation should also subject Bonneville’s transmission to FERC
regulation that is equivalent to FERC regulation of investor-owned
utilities."
- "[A]ny separation of generation and transmission – whether by
administrative or legislative means – be achieved in such a way that it
does not jeopardize or diminish the legal obligation and ability of
Bonneville to meet fish and wildlife and other obligations."
- ". . . maintain the [transmission] system’s reliability. . .
."
- Transmission separation should not increase the cost of transmission or
shift costs among transmission users.
Principles
The group discussed a set of tentative principles suggested by the staff and
raised some of them to the level of goals (numbers 2 and 5 above). The group
took up the tentative questions and issues suggested by the staff but decided to
examine and assign some of the tasks in the work plan, returning to questions
and issues later to make sure they’re all covered.
Assignments
The group formed two subgroups to begin work on Tasks 2 and 3 of the workplan:
- The Task 2 subgroup will examine existing statutes and other relevant
materials for obstacles to effective separation of Bonneville transmission
from its power marketing function and participation in an independent grid
operator. Bonneville has done significant analysis in this area; the group
has asked Bonneville to make its analysis and the documentation on which the
analysis is based available. The subgroup also requested that Bonneville
establish a "documents room" in which the relevant statutes,
legislative history, contracts and agreements would be made available to the
work group members.
- The Task 3 subgroup will not begin by "formulating alternatives for
separating BPA’s financial funds..." as laid out in Task 3. Instead,
it will examine Bonneville’s current treatment of costs of different
categories, as the first step in understanding alternative approaches to
separating the Bonneville fund into components that could be assigned to
separated functions. The subgroup asked that past Bonneville work on ways of
achieving effective splitting of the Bonneville fund be made available.
Future meetings
At the next meeting, the work group will be briefed by Bonneville staff on
Bonneville work regarding the legal issues involved in separation and the
alternative means of splitting the Bonneville fund. The rest of the meeting will
be devoted to development of an issues list; a draft list suggested by staff is
attached.
The group adopted a tentative schedule of meetings the first and third
Tuesday of each month. This schedule is linked to the meetings of the Federal
Power Marketing Subscription Work Group, which are the first and third
Wednesdays of each month, so that attendees can reduce travel cost and
inconvenience.
The next meeting of the work group is scheduled for April 15, 1997 at the
Northwest Power Planning Council offices. People who would like to join the work
group or either of the subgroups should contact Ken Corum at the Northwest Power
Planning Council (503-222-5161 or ).
Initial List of Questions and Issues -
subject to modification after review
- What conditions have to be met in order for Bonneville to participate as
fully as possible in the independent grid operator?
- What are the alternatives for separating Bonneville’s generation and
transmission?
- What are the implications of the separation alternatives for the
membership and possible role of the federal transmission entity in the
independent grid operator?
- Will the transmission entity be able to continue federal borrowing? If
not, how would it acquire funds?
- What will the entity’s relationship be to other federal entities such as
OMB?
- What are the transmission entity’s responsibilities to fish recovery and
other public purposes?
- How can such an entity be formed and maintain tax exempt status and
security for Supply System and other third party bonds?
- How can FERC regulation equivalent to that to which investor-owned
utilities are subject be accomplished consistent with the principles of
security of treasury debt and fish and wildlife obligations?
- Are there practical limits to "wire charges" for fish and public
purposes before bypassing occurs? How are those limits affected by different
pricing approaches?
- What structure and governance should the federal transmission entity have?
The structure should be flexible enough to accommodate what ever
relationship develops between an independent grid operator and the federal
transmission entity.
- What kind of public accountability and responsibility should the federal
transmission entity have?