THE MONTANA ELECTRICITY UTILITY INDUSTRY
RESTRUCTURING AND CONSUMER CHOICE ACT
SB 390
SUMMARY
(provided by Alan Davis, Montana DEQ and John Hines, NW Power Planning
Council)
Customer choice. On or before July 1, 1998 investor owned electric
utility customers with loads greater than 1000 kilowatts, or a customer with
with loads greater than 300 kilowatts per meter that aggregate to 1000 kilowatts
or greater, must have the opportunity to choose an electric supplier.
- As soon as administratively feasible, but before July 1, 2002, all
remaining investor owned utility customers must have choice.
- The Public Service Commission (PSC) may extend the date for 2 years if it
finds that it is not administratively feasible or that there isn’t
workable competition.
- Beginning July 1, 1998, utilities must run pilot programs offering
customer choice for residential and small commercial customers.
- Montana Dakota Utilities may defer choice until 2006.
Investor owned utility transition plan filing. Investor owned
utilities must file a transition plan with the PSC 1 year before any customer is
entitled to choice.
- The PSC must hold a contested case proceeding on the plan and afford all
parties the opportunity for a hearing before issuing a final order either
approving, modifying, or denying the plan.
- The PSC must make a decision on the plan within 9 months, unless waived by
the utility.
- The transition plan must contain: an outline for an orderly transition to
choice for all customers, a method for assigning customers that do not chose
suppliers, an educational program for their customers, and a plan for
implementing universal system benefits programs.
Investor owned utility functional separation. Investor owned utilities
must functionally separate the utility’s electricity supply, transmission ,
distribution and energy services operations.
- The utility must make its transmission and distribution facilities
available for all electricity suppliers and customers on a nondiscriminatory
and comparable basis.
- The utility must adopt and comply with a code of conduct consistent with
the Federal Energy Regulatory Commission’s code of conduct.
Investor owned utility power supply during the transition. On the
effective date of the PSC’s order implementing a transition plan, an investor
owned utility must remove its generation assets from rate base.
- During the transition to choice, the utility may offer cost-based supply
service for those that do not have choice or have not chosen.
- If the transition period is extended, so is the cost-based supply
contract.
- If an investor owned utility intends to be an electricity supplier through
an unregulated affiliate, the affiliate must be licensed as a supplier.
Investor owned utility transition cost recovery. The PSC shall allow
recovery of transition costs. The costs that may be recovered include:
- The unmitigable above market costs of qualifying facility contracts,
including buy out or buy down costs;
- The unmitigable costs of energy supply related regulatory assets and
deferred charges; and
- For a 4 year period, the unmitigable costs of investor owned utility owned
generation and power purchase contracts.
- The utility must make reasonable efforts to mitigate the costs
- Upon PSC approval, the transition costs are to be recovered through a non
bypassable charge on all customers, except for new loads of 1,000 kilowatts
or greater first served by the utility after December 31, 1996.
Investor owned utility rate moratorium. An investor owned utility
shall institute a rate cap during the transition to competition.
- Beginning July 1, 1998 there is a 2 year rate moratorium for all
customers.
- After June 30, 2000, rates for customers that do not have choice on July
1, 1998 cannot be increased, except for transmission and distribution rates
subject to PSC approval. Power supply costs are capped for these customers
until June 30, 2002.
- There are moratoriium exemptions for: increased universal systems benefits
charges in excess of current revenues; for an extraordinary event resulting
in a 4 percent or more increase in annual revenue requirement--8 percent of
power supply costs in the last two years of the rate moratorium, and for
increases or decreases in state and federal taxes in excess of rates of
inflation.
- During the transition, public utilities may not charge rates or collects
costs higher than they would reasonably expect to recover in rates if the
current regulatory system had remained intact.
Rural electric cooperative option of choice. Rural electric
cooperatives have the choice of opting in or out of offering their customers
choice.
- If a cooperative opts in, it must certify to the PSC that it has adopted a
transition plan consistent with the provisions of the act, but essentially
the same as the investor owned utilities.
- If a cooperative opts out, it is precluded from accessing the distribution
system, and thus customers, of other utilities that have opened their system
up without a preexisting contract.
- A cooperative must participate in the universal systems benefits program
whether it opts in or out.
Universal systems benefits program. A universal systems benefits
program is established as a charge to the meters of all utility customers to
ensure continued funding of energy conservation, renewables and low-income
energy assistance programs. Program costs shall be recovered through a charge
assessed at the meter for each local utility customer.
- Beginning July 1, 1999 and until July 1, 2003, 2.4 percent of each utility’s
1995 retail sales revenue is established as the funding level for universal
systems benefits programs.
- A minimum annual funding requirement for low income energy and
weatherization assistance is established at 17 percent of each utility’s
annual universal system benefits funding level.
- Customers with loads greater than 1000 kilowatts pay the lesser of
$500,000 or .9 mills per kilowatt hour purchased.
- Utilities and large customers receive credit toward their universal system
benefits obligation for their internal programs.
- If a utility’s or large customer’s credit does not satisfy the annual
funding requirement, then it shall make a payment to the universal systems
benefit fund or the universal energy assistance fund.
- Cooperatives may collectively pool their credits statewide.
- Investor owned utilities and cooperatives must file annual reports to the
transition advisory committee created by this bill.
Public Service Commission regulatory responsibilities. The PSC shall
continue to regulate the retail transmission and distribution system within
Montana after it issues a final order on a utility’s transition plan.
- The PSC may find that workable competition does not exist and continue the
regulation of electricity supply by distribution services providers as a
cost-based supply contract for a period of no more than 3 years.
- The PSC must determine whether competition is sufficient to inhibit
monopoly pricing or anticompetitive price leadership.
Licensing of electricity suppliers. The PSC shall license electricity
suppliers and enforce their licensing provisions.
- All electricity suppliers must be licensed by the PSC before offering to
sell to customers in Montana.
- The PSC must make sure that electricity supply is offered and is adequate
in terms of quality, safety, and reliability.
- The PSC may suspend the license, impose penalties, or both if the PSC
finds the electricity supplier violates the provisions of this act.
- Slamming or unauthorized switching of customers is specifically
prohibited.
- Electricity bills must disclose costs to customers of each cost component.
- Reciprocity is required of distribution entities.
Legislative transition oversight committee on electricity restructuring.
A legislative transition oversight committee on electricity industry
restructuring is created.
- There are 8 voting legislative members, two from each house from each
party.
- There are 12 nonvoting advisory members from industry, customer groups,
and other affected interests.
- The transition oversight committee shall analyze and report to the
Governor and members of the legislature on the status of electricity
industry restructuring in the state, the transition to effective
competition, the need for further consumer protections in the state,
recommend legislation to further promote restructuring, and make
recommendations on universal systems benefits programs.
Tax study. The revenue oversight committee is to analyze the tax
implications of restructuring and report to the Legislature with legislative
recommendations on the statutory tax changes that are necessary as a result of
restructuring.
Transition bond financing. Utilities are allowed to apply to the PSC
for a financing order to issue transition bonds to recover certain transition
costs.
- The cost savings from issuing bonds must benefit customers.
- The bonds are secured by a non bypassable charge on all customers that
creates a revenue stream to retire the bonds.
- The bond term must not exceed 20 years. d. Rural electric cooperatives
that opt in may also bond for recovery of stranded costs.
Territorial integrity act modifications. The territorial integrity act
is modified from who has responsibility to serve loads to who has responsibility
to connect the load.
- It creates a rebuttable presumption that the nearest line is the
least-cost line to build.
- There are provisions for the PSC to approve agreements between competing
utilities that might serve the same loads.
- There are special provisions for dealing with annexed new areas of cities.