|
|
|
Letter to BPA regarding project funding adjustments for FY 2003 accrual
limits
Related link: Spreadsheet of
adjustments (90k PDF)
June 20, 2003
Ms. Sarah McNary
Manager, Fish and Wildlife
Bonneville Power Administration
P.O. Box 3621; KEW
Portland, Oregon 97208
Dear Ms. McNary:
The purpose of this letter is to advise you of the Council's decision
with regard to project funding adjustments for fiscal year 2003 accrual
limits. The details of this decision and the events leading to it are
described below.
A secondary purpose of this letter is to assist in informing the
project sponsors and other interested parties of the status of Council
actions on this request. The following explains the action taken at the June 2003
meeting.
In December 2002, the Council agreed to help the Bonneville reduce or
defer its fish and wildlife spending in fiscal year 2003 in response to
the agency's financial crisis. The Council employed the dual
objectives of containing costs within $139 million and maintaining
support for the project work it approved in past provincial review
decisions. This was achieved by establishing a 2003 accrual based budget
plan, based on project accrual estimates that totaled $139 million. The Fiscal
Year Accrual Budget Estimate by Project and Contract Report was
submitted to Bonneville by the Council on February 21, 2003. In
developing this plan, Council staff, Bonneville and CBFWA agreed that a
project spending tracking system and a reallocation system were needed
to evaluate projects that are likely not to accrue their planned budget
amounts and make these funds available to projects that were severely
impacted by the 2003 decisions and need additional funds.
Staffs from Bonneville, CBFWA and the Council, utilizing previous and
newly developed worksheets,
identified many projects that needed funding adjustments for Fiscal Year
2003 accrual limits, and presented this information to the Council at
their meeting in June.
Council Action
The Council recommended that budget adjustments, totaling $4,432,210
be implemented for 2003. The project adjustments, and the amount
recommended by the Council are detailed in Table 1 (attached).
Projects in Table 1 are organized into several categories. The
Council took specific action with regards to two of these categories.
For category ?3? Bonneville has estimated a lower accrual estimate
than the Council's
estimate. The Council requests that Bonneville confirm with all project
sponsors that they are in agreement with the reductions. The Council
recommends adopting these adjustments only if project sponsors agree
that the adjustment is appropriate.
Projects in category ?4? are those where a ?within year
reallocation? or scope change and funding increase are proposed. The
Council recommends that Bonneville only approve the requests that stay
within the original provincial allocated budget.
Categories of projects for budget adjustments:
1. FY 2002 accrual (spending limit) impact to 2003 (increases).
$7,683,909
This category of project is by far the largest. Examples of how FY
2002 may have impacted FY 2003 include projects where the end-of-year
accrual estimates were inaccurate or not completed, ,
bills came in late from subcontractors, or bills from sponsors were late
in getting to Bonneville. In particular, invoices from federal agencies
are often submitted to Bonneville as late as one year after the work
occurs. This situation has not been an issue in past years when
carry-over was allowed.
2. FY 2003 contracted amount different than Council spending limit
(increases or reductions). $238,535
For these projects, Bonneville has issued contracts with a different
spending limit from the Council's estimate. In some instances,
objectives and tasks have been transferred between contracts or projects
by Bonneville COTRs. Realignment of funds associated with these
objectives and tasks are necessary. .
3. FY 2003 accrual correction (reduction). $3,655,799).
Projects in this category are those where Bonneville has estimated a
lower accrual estimate than the Council's estimate, and has provided
justification. Council has not yet been able to confirm with all project
sponsors that they are in agreement with the reductions. The Council
recommends adopting these adjustments only if project sponsors agree
that the adjustments are appropriate.
4. Within year reallocation/scope change (increase). $54,529.
These are projects where either a change in scope has been identified
with and increase in funding requested or where an increase is requested
in order to meet the existing scope of work. The Council recommends only
approving requests that stay within the original provincial allocated
budget.
5. Capital. $1,086,460
There are five projects in this category that we propose to change
the capital designation (4 from capital to expense, and 1 from expense
to capital).
6. Close outs. $90,926.
There are five projects in this category that have accrued actual
costs and are designated for closure.
7. Other. $701,038.
This category includes three projects that are considered BiOp
critical, and Bonneville estimates a larger accrual from the Council's
February table.
8. Phase 3. ($1,767,388)
Phase 3 includes projects that were originally recommended by the
Council for funding during the provincial review but implementation has
been deferred due to the 2003 fiscal crisis.
General FY 2003 budget information
The FY 2003 budget was developed using several placeholders. They are
outlined below.
2003 Budget placeholders
|
Allocated Spending Cap
|
$116,229,133
|
|
RM&E Placeholder
|
$2,742,500
|
|
ISAB/ISRP
|
$900,000
|
|
Subbasin Plans
|
$4,300,000
|
|
BPA overhead + project support
|
$12,000,000
|
|
APRE/HGMP
|
$1,300,000
|
|
TOTAL
|
$138,729,133
|
|
$138,729,133
|
Total budget from above table
|
|
$4,432,210
|
Adjustments
|
|
$143,161,343
|
Revised total
|
|
-$2,199,458
|
Explore capitalization of 2 projects
|
|
-$2,742,500
|
RM&E placeholder remaining
|
|
$138,219,385
|
TOTAL
|
Budget adjustments approved by the Council at their June meeting
total $4,432,210. The Council recommends that Bonneville consider
capitalizing Projects
#1996-043-00
($1,002,360) and #1983-319-00
($1,197,098) for a total of $2,742,500. The remaining placeholder for RM&E
is $2,742,500. Assuming capitalization of the above projects the overall
total FY 2003 budget is within the $139 million spending limit.
From an initial look at the Bonneville accrual tracking report
(05/21/03) it appears that many (103) projects have billed less than 30%
of their allocated budgets, even though, at the time the report was
prepared, we were 64% of the way through FY 2003. At the Council meeting
it was explained by Bonneville that
slow sponsor billing may account for the difference. The Council
is very concerned that slow billing in fiscal year FY 2003 will cause a
fiscal burden on 2004, similar to the situation that occurred in FY 2002
and 2003. In addition, the Council understood that in order to manage
the Fish and Wildlife Program budget to $139 million, tools would
be available to identify slow moving projects and reallocate funds to
other projects, in order to maximize the work accomplished in FY 2003.
The Council requests that Bonneville investigate projects that appear to
be moving slowly and identify the cause. Along similar lines, the
Council requests that Bonneville also investigate projects that are
nearing their accrual limit for 2003, and ensure that these projects do
not spend more than their allocated accrual limit identified in the
Council's February, 21, 2003 decision. The Council looks forward to an
update on this issue at the July Council meeting in Warm Springs,
Oregon.
Sincerely,
Doug Marker
Director
Fish and Wildlife Division
^ top
|
|