851 SW 6th Ave, Suite 1100
Portland, Oregon 97204-1348
503-222-5161 fax 820-2370
Process for the Acceptance of Energy Savings Protocols
Background
The RTF's deemed savings estimates are based on well-documented evidence,
namely generally accepted engineering calculations adjusted to the findings of
independently reviewed evaluation report and metering results. For those
measures which can not be reliably predicted through deeming the C&RD
requires evaluation/verification protocols. The process for estimating savings
based on these protocols should have comparable assurance of reliable energy
savings to those estimated as deemed savings.
The protocols described in Appendix P are guidelines/general approaches and
were not intended to provide detailed instructions on how to conduct the
credible analysis required to establish verified energy savings. They do not
deal with critical issues, such as, sampling, outlier methodology, or definition
of measurement periods which are key factors in estimating energy savings. A
process is needed to put in place a detailed protocol that tailors the general
approach in Appendix P to specific projects.
Issues
The process for submitting, reviewing, and confirming specific measurement
and verification plans involves the following issues:
- Is there a review process for the verification plan or for the
verification report?
- Who conducts the review process ? the RTF (by members, staff or
contractors) or by Bonneville?
- Does the review process include discussions with sponsors and include
suggestions by the reviewers for revisions to the verification plan?
- Is the review process only concerned as to whether the verification plan
is consistent with the principal and general protocols in Appendix P?
- Is it necessary that the verification report and results be reviewed and
accepted?
- How would revisions to an approved verification plan be made?
- If the review process is extensive, should the sponsoring utility or
Bonneville pay for that cost and how should the sponsor recover that cost?
Alternative Approaches for Accepting Energy Savings Protocols
- Alternative 1: The sponsoring utility would select a general protocol from
Appendix P. There would be no review of the specific verification plan for
the project but the utility would keep them as part of the program record.
Discussion: This approach minimizes verification requirements and maximizes
sponsor flexibility. The RTF was asked to provide a methodology for estimating
energy savings for those measures that can not be deemed. This approach would
delegate much of this responsibility for saving estimation to the sponsors.
- Alternative 2: Bonneville would assign engineering staff to review the
project protocol. They would determine if the preliminary engineering
estimate of savings was reasonable, if the verification plan is adequate.
Subsequently staff would review the verification report and accept the final
results.
Discussion: This approach follows the general format of Bonneville's
Energy Savings Plan program. This review would make the verification plan and
results credible but Bonneville has requested the RTF's evaluation
responsibilities support the C&RD and take the technical lead in
estimating energy savings.
Making appropriate Bonneville staff available to meet this need may be
difficult.
- Alternative 3: This approach would involve verification review and
acceptance by an RTF contractor. The sponsoring utility would submit the
engineering proposal including an engineering estimate of savings. The
sponsor would select one of the RTF's verification methods (Appendix P) or
propose one of their own. The verification protocol would be tailored to the
specific project. The protocol if necessary would contain a metering plan
and sampling method including measure of precision and reliability. The RTF
verification contractor would check if the engineering estimate of savings
is reasonable and if this specific protocol was consistent with the
principle and methods described in Appendix P. The contractor would suggest
modifications if something was missing or inappropriate and approve the
verification plan. The contractor would review the final report to determine
if this methodology should be recommended to others for doing similar
projects and to collect information for developing additions to the RTF's
list of deemed measures. The contractor's responsibility would not be to
approve the report or check for compliance with the verification plan.
Discussion: In this approach the determination of the savings methodology
would be the responsibility of the RTF and the implementation of the
verification plan would be the responsibility of the sponsoring utility. This
approach would be similar to the deemed savings methodology in which the RTF
determines energy savings estimation but adherence to measure specifications
is the responsibility of the utility. This approach would require the RTF to
administer and provide guidance to a task order pool of verification
contractors.
^ top