| 10:00 am |
Introductions and Review of 1/17/08 Technical Committee Notes (John Fazio/Mary Johannis)
|
| 10:15 am |
Synopsis of 1/29/08 Steering Committee Meeting (Fazio)
- PNW Resource Adequacy Standard recommended to Council for Adoption
- Support for Regional Sustained Hydro Peaking Capacity Analysis
|
| 10:30 am |
Status of Wind Capacity Value Assessment Effort (BPA/Jeff King)
- BorisMetrics Data Simulation
- BPA Analysis
|
| 11:30 pm |
Lunch |
|
12:30 pm |
Regional Sustained Hydro Peaking Capacity Contract (Johannis/Eric King)
- Phase I/II Approach or Hydro Subgroup
- Proposed Summer and Winter Runoff Conditions
|
|
1:30 pm |
Defining Variables for the Adequacy Standard (All)
- Hydro Peaking Capacity
- Normal Temperature Load
|
| 2:00 pm |
Status of GENESYS Model Improvement and Validation Effort (Fazio)
- Planned Model Enhancements
- Federal GENESYS
|
| 2:30 pm |
Major Tasks Remaining (All)
- Utility Guidance
- Event Thresholds
- Combination Energy/Capasity LOLP
- Decoupling Water and Temperature
|
| 3:00 pm |
Schedule Next Meeting
|