Energy arrow Power Supply arrow

 


Regional Power Supply Adequacy/Reliability Study
Report on the Second Advisory Committee Meeting

January 14, 1999

The Advisory Committee held its second meeting on Thursday, January 14 in the Council's offices.  Members in attendance were: Dick Adams, PNUCC; Ken Dragoon, PacifiCorp; Chris Elliott, Northwest Power Pool; Rich Lauckhart, Northwest Power Enterprises; Phil Sher, PNGC; Carol Opatrny, PPC; Audry Perino, BPA; Jack Williams, Oregon PUC; Steve Kerns, BPA; Marty Howard, McCullough Associates/CRITFC; Steve Knudsen, PG&E Gas Transmission; Frank Afranji, PGE; Tim Misely, BPA; Lon Peters, Public Generating Pool.

Also in attendance were:  Mike McCoy, Power Systems Research; Mike Niman, PGE; Christine Wallat, Enron; Michael Schimoeller, Enron; Charles Grist, Oregon Office of Energy; Kurt Granat, PacifiCorp; and Steve Kern, Arizona Public Service.

Assessment of Northwest Electric Reliability ? Winter 1998-99

Chris Elliot led off the meeting with a report on the Northwest Power Pool's recent analysis of electric reliability for this winter.  This is a spread sheet analysis looking at the ability to meet peak and weekly energy loads during an extreme cold event, focusing on estimated loads and resources for a week in February.  February was chosen because there is less hydro capability in that month.  The Power Pool estimated the extreme weather loads using data from the February ?89 event.  They estimated a peak load of 45000 MW and an energy load for the week of 36700 aMW.  Coincidentally, the period of Dec. 20 ? 22, 1998 qualified as a cold snap, although the fact that it included a weekend day and part of Christmas week probably meant that loads were lower than they might otherwise have been.  The observed peak of 42300 MW gave some confidence to the estimates for February.  In addition, winter transfer capabilities were more than sufficient for imports during the December event.  The analysis made conservative assumptions for import capability.  It assumed that there were no imports available from Canada although imports were being made during the December event.  There was also no assumption regarding interruptible loads.

The key conclusions were:

  •  Peak loads could be met, but with little margin.
  • To meet higher loads for an extended period of a week or two, drafting reservoirs below planned levels would allow meeting the loads and reservoir levels could be subsequently restored to planned levels by purchasing imports.

It was noted that if Centralia were shutdown, the situation would have been significantly worse.

Chris emphasized that a by-product of restructuring is that it is getting more difficult to do these kinds of analyses.  Companies are no longer providing information on projected loads and resources, necessitating the making of a lot of assumptions by the analysts.
 

DREW Analysis

Audry Perino briefed the group on the work done for the Drawdown Regional Economic Workgroup (DREW).  The DREW analysis is intended to assess the economics of drawing down the four Lower Snake dams. Included in the analysis is an assessment of the adequacy of power supply with the four Lower Snake dams and with them replaced with combined cycle combustion turbines.  The analysis calculated the MW of CCCTs it would take to replace the four Lower Snake Dams and looked at the distribution of the amount of unserved load (driven by hydro variability) with and without the dams at different points in the future.  Planned and forced outages are accounted for by derating the system capability.

The amount of new resources developed is determined using an algorithm that minimizes total cost, including the cost of unserved load.  The key point as far as our study is concerned is that the amount of resources added was found to be extremely sensitive to the value assumed for unserved load.  The basic analysis used the same supply curve of demand side resources (the amount of demand reduction available as a function of price in mills/kWh) used in the Council's earlier analysis of market prices using the Aurora model.

Step % of Area Peak Demand  

 Cost -- 1997 $/MWh

Step 1 -- 0 to 5%

 50

Step 2 -- 5% to 10%

100

Step 3 -- 10% to 15% 

150

Step 4 -- 15% to 20%

250

Step 5 -- 20% to 25%

500

Step  6 -- Over 25%

1000

This supply curve is as good an estimate as Council staff was able to make, but there is relatively little real data and experience to back that up.  The sensitivity to this assumption was tested assuming all unserved load has a very high price (5000 mills/kWh).  Under these assumptions, almost twice as many aMW of new resources are developed (16000 aMW compared to 9000 by 2010 ? Note that these are the total AMW developed to meet load growth, not the amount developed to replace the dams).  As a result, the average amount of annual unserved load (averaged over 50 water years) in 2010 drops from 80-90 aMW to a few tenths.  In other words, the amount of new resource development and hence the amount of load that analysis says would go unserved is extremely sensitive to something about which we know relatively little, the value of unserved load.

Spreadsheet Reliability Assessment Model

Ken Dragoon presented information (see presentation) on a spreadsheet reliability assessment model he developed and used while at Bonneville.  The model uses At Risk running with an Excel spreadsheet to provide a probabilistic assessment of reliability.  The model uses a basic load-resource balance sheet (page 3 in the presentation) with probability distributions for stochastic variables such as hydro conditions, forced outages, and variations in loads.  The model performs a large number of load-resource balance simulations letting the stochastic variables vary.  The output is a distribution of surpluses and deficits, from which various reliability indices can be calculated.

Ken reviewed several possible indices of reliability and the ambiguity associated with some of the reliability standards (e.g., what does the PNCA standard of one day in 20 years really mean?).  He emphasized the importance of expressing the results in terms decision-makers can understand.  He suggested translating reliability indices into a surplus or deficit (in MW) for one or more standards.

It was noted that the loads and resources are inputs to the model ? there is no consideration of resource expansion ? and no consideration of economics.  However, the advantage of such a model is its transparency.  it's relatively easy to understand what's going on.  It was suggested that the spreadsheet model be used as a check on the more sophisticated analysis.  If there is not good agreement it should be relatively easy to isolate the cause.

Ken reiterated the problem of getting good data with which to do reliability analyses, noting that this is an institutional problem of restructuring.

?GenESys?

Pete Swartz described the progress in developing ?GenESys? (Generation Evaluation System), the modeling system being developed for this project.  The model combines elements of a number of different Council models and will be able to address generation reliability and the associated economics.  Good progress has been made.  Pete demonstrated the operation of the model.  It appears to run quite efficiently and provides a great deal of flexibility in specifying the inputs, run parameters and output information.  However a great deal of work remains to be done.  Pete is now looking at mid-February for having the modeling relatively complete.  A group of those advisory committee members with a particular interest in the modeling will be meeting with Council staff to review progress and assess if this is the proper direction for the modeling.

A question was raised regarding what to use for and how to treat contracts for export.  The recommendation was to use what in the PNUCC Northwest Regional Forecast and/or the White Book, acknowledging that these are likely to be increasingly incomplete or inaccurate.

Another question was how to treat those contracts in a reliability analysis.  Can we assume that in a period of tight supply in the Northwest, Northwest generators with contracts to supply loads outside the region would be able to ?counter-schedule,? i.e., make purchases in the export region (depending on the availability of capacity) to serve their contract loads while using their NW generation to meet regional needs??

A caution was expressed that that might not be the case.  To do so might mean that the out-of-region customer would have to accept service over a transmission path for which the supplier does not have firm rights.  The customer might not be willing to accept this.

A question was raised that if you saw a cold snap coming, wouldn't you get on the phone and try to firm up the ability to counter schedule?  Yes ? but you might not be able to.

The comment was made that we have to be very careful about assuming that we can max out the intertie capacity when we need it.

It was suggested that we start out with the firm loads and resources in the NW and then see how much you would have to lean on other sources like displacing firm exports, making imports and curtailing load.
 

Policy/Institutional Issues

Wally Gibson presented a rough draft aimed at structuring the policy and institutional issues associated with assuring an adequate and reliable power supply during the transition to a fully competitive power market (attached).  It was acknowledged that that transition was underway but how far and how fast it might proceed is an open question.

Most were comfortable that markets, left to their own devices, would develop to address the adequacy/reliability issue.  There are concerns, however, that markets won't be left to their own to develop.  This could be for reasons unrelated to reliability.  Or, it could be that extreme prices and/or supply disruption associated with a period of tight supplies could result in interventions that might be counter-productive and that might prevent markets developing to the point that they can adequately address reliability issues.

One member stated the goal of this study roughly as follows:  ?What are the impediments to getting from where we are today (partial restructuring) to a world where there are perfect markets, perfect contracts.  And what do we do about it??

Wally is seeking comment from the committee and others on this draft.

The role of quantitative analysis in this issue is open to question.  The goal is to be credible and understandable to decision-makers.  How sophisticated does the analysis have to be to meet that goal?

Next Meeting

The next meeting of the advisory committee was schedule for the afternoon of February 18th, 1:30 ? 5:00 at the Council's offices.

^ top