Council Home
Energy
Comprehensive review archive
Discussion
In preliminary discussion with Steering Committee members, there was near unanimity that Bonneville should neither acquire new resources nor be responsible for net requirements of its customers in the future. A few members of the Steering Committee would modify that limitation by allowing acquisition by specific contract at the request of a specific customer or to make strategic acquisitions to enhance marketing ability and Treasury repayment.
Beyond that there was little consensus other than that the work group should take a broad look at alternative models for marketing federal power and at the implications of those models for a number of factors. One list of models was originally discussed by the Steering Committee and has been rearranged slightly for the work group's specific tasks.
Market power is both a general market structure question and a specific issue for Bonneville, related to the coordinated hydro system. There was uncertainty about the potential magnitude of the problem. Information from the work group may help to inform the overall choices the Steering Committee.
The following issues were taken from the list put together by the Steering Committee. The specific tasks are derived from them, within an overall framework emphasizing the issue of alignment of risk and benefits associated with marketing federal power.
Issues
Tasks
Each of the models that the Steering Committee has selected should be further specified by the work group, with the intent of maintaining the essential features selected by the Steering Committee for examination, while providing a fully fleshed-out model that allows all the implications of the model to be seen. The models are intended to cover the range of issues with a small list of alternatives. Alignment of costs and risk bearing with potential benefits is the framework for the alternatives.
A. Muddle through (take no further actions)
This is the base case and assumes no additional institutional modifications from the current situation other than an administrative split of generation and transmission.
B. Competitive
This model is distinguished by focusing changes only on Bonneville's power marketing rights and obligations and not any of its current costs. Changes could include expanding its rights and reducing its obligations, with the goal of making Bonneville competitive at current cost levels.
C. Minimize risk by stranded cost charge
This model is distinguished by focusing on restructuring Bonneville's costs and/or revenues so that costs to be recovered by power sales are at or below market levels, while keeping power marketing rights and obligations relatively the same as are now in place.
D. Allocation of marketing rights
This model focuses on transferring the marketing rights to some other entity while maintaining some level of below-market prices for some or all customers in the region. This would likely be accomplished by the Treasury absorbing risk or potential loss.
E. Sale or lease of marketing rights
This model focuses on transferring the marketing rights and creating a market-priced and market-pricing entity.
F. Other
The above list is not intended to be exclusive or limiting and the committee will encourage other proposals.
A. Treasury repayment
B. Risks and benefits
C. Transfer of marketing rights (if applicable)
D. WPPSS
E. Columbia River Treaty
F. Fish and wildlife responsibilities
G. Other contracts
H. Compatibility with a competitive market
I. Public preference
J. Achievement of regional policy goals
K. Transition
L. Other issues?
3. Define the magnitude of the market power problem for federal power marketing rights
Implications for, and links to, other work groups
Schedule
The work groups are scheduled to complete their work by July 11, a period of about 100 days from April 1. By the May 9 meeting of the steering committee, the workgroup should be prepared to give a progress report. The report should include the group's strategy for addressing the issues assigned to it, tasks that have been assigned to subgroups, research and data requests issued by the group and staff or contractors responsible, and a detailed listing of the issues and alternatives that are being studied along with some preliminary findings.
At the June 6 steering committee meeting, the group should be prepared to present its preliminary findings regarding alternatives it has evaluated including the pros and cons relative to the important objectives of the regional review.
At the July 11 steering committee meeting, the group's work should be done. A detailed written report should be available for the steering committee to use in its deliberations. In addition to the facts gathered and the pros and cons and feasibility of the alternatives examined, it should address the necessary steps to be taken to implement each alternative with a discussion of feasible strategies for phasing in the alternative.
| Task 1 | April | May | June | July |
|---|---|---|---|---|
| Report to Steering Committee | 9 | 6 | 11 | |
| Define the specific models for marketing federal power | ------------- | |||
| Interim review by Steering Committee of specific models | ----- 18 | |||
| Final approval by Steering Committee of specific models | -X |
| Task 2 | April | May | June | July |
|---|---|---|---|---|
| Report to Steering Committee | |
9 | 6 | 11 |
| Evaluate each of the models with regard to each issue | -------- | ------------ | ---------- | |
| Prepare final report | ----- | - X |
| Task 3 | April | May | June | July |
|---|---|---|---|---|
| Report to Steering Committee | |
9 | 6 | 11 |
| Council staff prepares background report for Steering Committee and work group | ------------- | --X | ||
| Evaluate substantive issue | ------------ | --------- | |
|
| Prepare final report | ----- | --X |
Discussion
The Steering Committee expects that its transmission workgroup will build on work already underway in the PNUCC transmission workgroup, and expects that the group will consist of the membership of the PNUCC group, expanded to include other interested parties. The Steering Committee identified a number of topics to be addressed by the workgroup. These topics include:
The steering committee did not specify the components of an appropriate definition of the transmission system, but subgroup discussions identified voltage as one means of categorizing lines as part of the transmission system or utilities' local distribution system. The sense of the steering committee appeared to be that line voltage might not capture all the important considerations, and the transmission workgroup should develop a clear definition to guide its work and to help the steering committee consider transmission questions.
There was agreement among the steering committee that while the transmission system will need to be at least administratively separated from generation, a greater degree of separation was likely to be necessary. The steering committee identified an independent grid operator as a way of accomplishing this greater degree of separation. The degree of control given to a grid operator is an area of interest to the steering committee. Some on the committee rejected dispatch of generation by a grid operator. In its discussion, however, the steering committee decided that while there was skepticism regarding mandatory pools and central dispatch, the committee needed more information before it could rule such options out. This should be an area of interaction between the transmission working group and the competition and customer choice working group.
The steering committee expressed interest in the effects of alternative methods of pricing transmission services. This interest included both the equity effects (shifting of transmission costs among all parties) and the efficiency effects (increased total value of services provided by the power system). The alternatives discussed included "postage stamp" and "zonal" pricing of transmission.
The steering committee heard that the separation of BPA's generation from its transmission could effect its ability to meet its financial obligations. It also heard that our region's choice of transmission system operation could affect neighboring power systems.
Primary Tasks
1. Define the transmission system.
2. Define the alternatives for organization and management of the transmission system -- evaluate the advantages and disadvantages of each alternative. The alternatives should include:
3. For these alternatives, evaluate the efficiency of operation and incentives for expansion and reliability of the transmission system.
4. For those alternatives that involve transfer of control or ownership of assets, examine possible methods of transfer and compensation for the current owners.
5. Evaluate the potential effect of wholesale market structure on efficiency of operation and incentives for expansion and reliability of the transmission system. This work should be coordinated with the competition and customer choice workgroup. Include the cases of:
6. Identify and evaluate alternative methods of transmission pricing (for example, postage stamp, zonal, hub and spoke, on/off charges, congestion pricing and secondary markets for unused transmission capacity).
7. Evaluate the effects the alternatives, for organization and management of the transmission system and for transmission pricing, might have on the power system's ability to accomplish its public purposes and meet its legal obligations. This work should be coordinated with the federal power marketing work group and the public purposes work group.
8. Identify the most important issues to be addressed in the transition from the present transmission system to the future system.
Schedule
The work groups are scheduled to complete their work by July 11, a period of about 100 days from April 1. By the May 9 meeting of the steering committee, the workgroup should be prepared to give a progress report. The report should include the group's strategy for addressing the issues assigned to it, tasks that have been assigned to subgroups, research and data requests issued by the group and staff or contractors responsible, and a detailed listing of the issues and alternatives that are being studied along with some preliminary findings.
At the June 6 steering committee meeting, the group should be prepared to present its preliminary findings regarding alternatives it has evaluated including the pros and cons relative to the important objectives of the regional review.
At the July 11 steering committee meeting, the group's work should be done. A detailed written report should be available for the steering committee to use in its deliberations. In addition to the facts gathered and the pros and cons and feasibility of the alternatives examined, it should address the necessary steps to be taken to implement each alternative with a discussion of feasible strategies for phasing in the alternative.
| Tasks | April | May | June | July |
|---|---|---|---|---|
| Report to Steering Committee | |
9 | 6 | 11 |
| 1. Define transmission system | --------- | -X | ||
| 2. Identify alternatives for organization and management of transmission system | --------- | -X | ||
| 3a. Evaluate these alternatives for their effect on efficiency of operation and incentives for expansion of transmission | ----------- | -------- | ||
| 3b. Prepare report to steering committee on pros and cons on alternatives | ----------- | ----------- | --X | |
| 4. Examine methods of transfer and compensation for assets | ----------- | --------- | ||
| 5a. Evaluate the potential effect of wholesale market structure on efficiency of operation and incentives for expansion of transmission | ----------- | --------- | ||
| 5b. Prepare report to steering committee on effects of wholesale market structure | ----------- | ----------- | --X | |
| 6a. Identify alternative methods of transmission pricing | --------- | -X | ||
| 6b. Evaluate alternative methods of transmission pricing | ------------- | --------- |
| Tasks | April | May | June | July |
|---|---|---|---|---|
| 6c. Prepare report to steering committee on pros and cons of pricing alternatives | ----------- | ----------- | --X | |
| 7. Evaluate effects of organization, management and pricing of transmission on system's ability to accomplish public purposes and meet legal obligations | ----------- | ----------- | ||
| 8. Identify transition issues | --------- | ----------- | ----------- |
There was less agreement about renewables. Some believe that the market will develop cost-effective renewable resources while others believe there are regulatory and market barriers to be overcome. The tasks for the work group include identifying the barriers to preservation of renewable resource options and renewables development; identifying strategies to overcome those barriers including RD&D and commercialization, and identifying the means of financing and administering those strategies.
Environmental costs were discussed. The mitigation of environmental costs that are legitimately attributable to the power system, including fish and wildlife costs, were acknowledged to be the responsibility of the power system. While there may be disagreement with specific mitigation requirements, establishing those requirements was generally believed to be the responsibility of the appropriate environmental regulators. The issue of governance of fish and wildlife mitigation is being addressed by the 180-Day Review. The risk associated with fish recovery requirements will be addressed by the Federal Power Marketing group. There does not appear to be any specific task for the work group on this issue. However, the implications of structural alternatives on the ability to fulfill environmental responsibilities should be a consideration for all work groups.
Opinion regarding treatment of Bonneville's public purposes, obligations and cost transfers such as rural development, irrigation, flood control, recreation, navigation, residential exchange and public preference was mixed. Some are concerned that these issues are so difficult as to prevent progress on other issues.
Others felt that it is necessary to address them. It was agreed that at a minimum, an effort would be made to identify and quantify these purposes, obligations and cost transfers. To the extent that the work group identifies significant issues, it should report these to the steering committee and seek direction as to whether the work group should explore conceptual alternatives. Bonneville has performed an initial assessment that has been delivered to the Steering Committee. The necessity of linkages between these issues and the work of other groups was noted. It is the responsibility of all work groups to consider the effect of alternatives on the ability of the system to fulfill public purposes.
Primary Tasks
1. Identify and evaluate alternative means of securing cost-effective conservation that are consistent with increasingly competitive electricity markets. Explicit evaluative criteria should be developed and utilized. Specific tasks include:
2. Identify and evaluate alternative means of preserving renewables as a long-term option and encouraging development of renewable resources.
The alternatives must be consistent with increasingly competitive electricity markets. Explicit evaluative criteria should be developed and utilized. Specific tasks include:
3. Public purposes, obligations and cost transfers.
Identify and estimate the costs of public purposes, obligations and cost transfers including rural development, low density discount, residential exchange, irrigation, flood control, low-income energy assistance, recreation, navigation, and public preference. Specific tasks include:
Implications for, and links to, other work groups
Maintain liaison with the groups considering federal power marketing, competition, and transmission to ensure that they consider the implications of the alternatives considered for the ability to support public purposes, obligations and cost transfers. Schedule
The work groups are scheduled to complete their work by July 11, a period of about 100 days from April 1. By the May 9 meeting of the steering committee, the work group should be prepared to give a progress report. The report should include the group's strategy for addressing the issues assigned to it, tasks that have been assigned to subgroups, research and data requests issued by the group and staff or contractors responsible as well as a report on the status of the initial work tasks.
At the June 6 steering committee meeting, the group should be prepared to present its preliminary findings regarding alternative strategies it has evaluated with respect to conservation and renewables as well as its assessment of the costs of public purposes, obligations and cost transfers.
At the July 11 steering committee meeting, the group's work should be done. A detailed written report should be available for the steering committee to use in its deliberations. It addition to the facts gathered and the evaluation of the alternatives examined, it should address the necessary steps to be taken to implement each alternative with a discussion of feasible strategies for phasing in the alternative. Proposed timelines for the tasks are shown below.
Conservation
| Task | April | May | June | July |
|---|---|---|---|---|
| Report to Steering Committee | 9 | 6 | 11 | |
| Develop work plan, information needs and assignments | ------X | |||
| Identify conservation market likely will and will not develop and kinds of market failure | ------------- | -X | |
|
| Identify and evaluate strategies for overcoming market failures | ------- | ----------- | X | |
| Identify and evaluate financing mechanisms, including implementation step | |
--------- | ------------ | --X |
| Identify and evaluate administrative mechanisms, including transition and implementation steps | |
----- | ------------ | --X |
| Document | |
|
------------ | --X |
Renewables
| Task | April | May | June | July |
|---|---|---|---|---|
| Report to Steering Committee | |
9 | 6 | 11 |
| Develop work plan, information needs and assignments | ------X | |
|
|
| Identify barriers | ------------- | -X | |
|
| Identify and evaluate strategies for overcoming barriers | ------- | ------------ | X | |
| Identify and evaluate financing mechanisms including implementation steps | --------- | ------------ | --X | |
| Identify and evaluate administrative mechanisms, including transition and implementation steps | ----- | ------------ | --X | |
| Document | |
|
------------ | --X |
Public purposes, obligations and cost transfers
| Task | April | May | June | July |
|---|---|---|---|---|
| Report to Steering Committee | |
9 | 6 | 11 |
| Develop work plan, information needs and assignments | ------X | |||
| Review Bonneville Analysis of public policies benefits and costs and modify list as appropriate. | ------------- | --X | ||
| Estimate cost of Public purposes, obligations and cost transfers and report significant issues to Steering Committee | ------------ | X | ||
| Explore conceptual alternatives for public purposes as directed by Steering Committee | ------------ | --X | ||
| Identify alternative means of supporting low income energy assistance | -------- | ------------ | ----X | |
| Maintain liaison with other work groups regarding implications of structural alternatives for public purposes | ------------- | ------------ | ------------ | -- |
| Document | |
----- | ------------ | --X |
Last modified: April 22, 1996
http://www.newsdata.com/enernet/review/documents/scope1.html
Copyright © 1996 Energy NewsData